Honam Semiconductor Cluster · geographic assessment

Honam (호남) Semiconductor Cluster · Gwangju military airport (광주 군공항)

The land fits. The timetable is the risk.

Samsung Electronics and SK hynix plan four memory fabs and about ₩800 trillion of investment on Gwangju's flat, state-owned airbase[S1, S3]. Production is targeted for June 2030, but only if 6.3 GW of power, 650 000 t/d of water and the airbase's departure arrive in sequence[S7, S11, S17].

₩800trillion announced by Samsung and SK hynix[S1]Plan · not yet spent
4 memory fabs, 2 + 2[S1]Planned
6.3GW power at full build-out[S11]Projected need
650 000t/d water at full build-out[S11]Stated need
8.26km² site, ≈2.5 M pyeong[S5]Designated 29 Jul 2026
Jun 2030 first mass production[S7]City target

FIG. 1The site and its supply lines

Click any feature for its value and source

Showing key links: water, power, airbase move, transport

Power: targets vs. projected demandGW

Each bar carries its own date; they are not simultaneous. Nothing new is built yet.

02468GWFull build-out need 6.3 GWS11Stage-1 supply target · end-2028 · Gwangju city3.1 GWS7Stage-1 via Sin-Jangseong · ministry/KEPCO plan, Jul 2026≈4 GWS13Projected cluster demand · 20311.57 GWS13Projected cluster demand · 20346.28 GWS13Hanbit nuclear plant · installed today5 875 MWS14
Supply target (not built)Projected demandExisting generation

Water: planned supply by staget/d

National plan, August 2026 revision; 650 000 t/d by 2030.[S8]

Stage 1350 000Dongbok Dam 300 000Juam Dam 50 000Stage 2300 000Naju Dam 100 000Reclaimed wastewater 200 000Full build-out, by 2030650 000 t/dEnd-2028 interim target 150 000 t/d (Gwangju city)S7

Hatched = reclaimed wastewater, for cooling. The city's long-run 1.06 M t/d differs from the national figure[S7]; see contested figures.

Nine factors

Details ↓

Critical path

Full timeline ↓
  1. Airbase site chosen (Done)[S3]
  2. Muan named relocation candidate (Done)[S18]
  3. Grid feasibility study waived (Done)[S12]
  4. Muan resident referendum (Pending)[S20]
  5. Transmission groundbreaking (Target)[S7]
  6. Airbase functions dispersed (Target)[S17]
  7. Fab construction begins (Target)[S7]
  8. Stage 1: 3.1 GW, 150 000 t/d (Target)[S7]
  9. First mass production (Target)[S7]
DonePendingTarget

Sequence

Everything after October 2026 is still a target

Decisions cluster in the summer of 2026. The infrastructure, the airbase move and production all sit to the right of the status date.

2026AprJulOct20272028202920302031203220332034scale compresses after 2027 →← Oct 2014: relocation first requested (S4; off scale)13 Oct 2026 · status datePolicy, law & site10 Feb 2026 — Semiconductor Special Act enacted. [Decided / occurred; S30]Special Act enacted1 Mar 2026 — National Assembly passes the Jeonnam–Gwangju integration act. [Decided / occurred; S31]Integration act passed29 Jun 2026 — “3 Mega Projects” report (대한민국 대도약 3대 메가프로젝트): ≈₩800 trillion and four memory fabs in the southwest; Chungcheong (충청) packaging hub, ₩81 trillion. [Announced plan; S1, S2]3 Mega Projects1 Jul 2026 — Jeonnam–Gwangju Integrated Special City (전남광주통합특별시) launches. [Decided / occurred; S31, S7]Integrated city launches6 Jul 2026 — Gwangju military airport chosen as the cluster site. [Decided / occurred; S3]Site chosen14 Jul 2026 — Two-year land-transaction permit zone takes effect around the site. [Decided / occurred; S22]Land-permit zone29 Jul 2026 — MOLIT designates ≈2.5 M pyeong as a candidate national industrial complex. [Decided / occurred; S5]Candidate complex11 Aug 2026 — Special Act enforcement decree in force. [Decided / occurred; S30]Decree in force25 Aug 2026 — Muan national industrial complex candidate (3.47 km²) designated. [Decided / occurred; S38]Muan complex candidateAirbase relocation17 Dec 2025 — Six-party joint statement on relocating the airbase to Muan. [Decided / occurred; S19]Six-party statement2 Apr 2026 — Ministry of National Defense names Mangun-myeon (망운면), Muan, as preliminary relocation candidate. [Decided / occurred; S19]Preliminary candidate14 Aug 2026 — Defense ministry details temporary dispersal to Yecheon, Jungwon and Seosan. [Decided / occurred; S17]Dispersal plan28 Aug 2026 — Mangun-myeon selected as relocation candidate. [Decided / occurred; S18]Relocation candidate22 Sep 2026 — Muan International Airport runway defects found; repairs to run to H2 2027. [Decided / occurred; S25]Muan runway defects≈Oct 2026 — Muan resident referendum on hosting the airbase (result not reported as of 13 Oct). [Target / pending; S20]Referendum (pending)End-2027 — Gwangju domestic flights move to Muan; Honam KTX phase 2 via Muan Airport. [Target / pending; S25, S4]Civil flights to MuanMid-2028 — Airbase functions temporarily dispersed to Yecheon, Jungwon and Seosan. [Target / pending; S17]Airbase dispersedDec 2032 — New military base at Muan completed. [Target / pending; S18]Muan base completePower & water14 Aug 2026 — Water plan revised to use reclaimed wastewater instead of two dams. [Decided / occurred; S8]Water plan revised1 Sep 2026 — Cabinet waives the preliminary feasibility study for the power-supply facilities. [Decided / occurred; S12]Grid waiver6 & 12 Oct 2026 — National Assembly audit: power and water disputes; stage-1 line target moved to 2028; KEPCO puts stage-1 cost at ₩1.4 trillion. [Decided / occurred; S11, S12]Audit: line target → 2028Jun 2027 — Transmission-line groundbreaking. [Target / pending; S7]Line groundbreakingSep 2027 — Sin-Jangseong (신장성) 345 kV substation completion. [Target / pending; S13]Sin-Jangseong substationEnd-2028 — Stage-1 supply: 3.1 GW of power and 150 000 t/d of water. [Target / pending; S7]Stage 1: 3.1 GW, 150k t/d2030 — Water supply capacity of 650 000 t/d. [Target / pending; S8]650k t/d water (2030)2034 — Cluster power demand reaches 6.28 GW (projection). [Target / pending; S13]6.28 GW demand (2034)Fabs & production30 Jun 2026 — Gwangju briefing: Amkor Technology Korea announces ≥₩1 trillion for advanced packaging. [Announced plan; S28]Amkor ≥₩1 tn2028 — Construction of the first two fabs begins. [Target / pending; S7]Fab construction (2028)Jun 2030 — First mass production. [Target / pending; S7]First mass production
Decided / occurredAnnounced planTarget or pendingStatus date, 13 Oct 2026
FIG. 2 Milestones by lane. Hover a marker for its full description and sources. Year-only targets (2028, 2030, 2034) are placed at the start of the year. The 2014 relocation request is off scale[S4].
Full chronology with sources
  1. Gwangju formally requests relocation of the military airport (approved 2016). [S4]
  2. Six-party joint statement on relocating the airbase to Muan. [S19]
  3. Semiconductor Special Act enacted. [S30]
  4. National Assembly passes the Jeonnam–Gwangju integration act. [S31]
  5. Ministry of National Defense names Mangun-myeon (망운면), Muan, as preliminary relocation candidate. [S19]
  6. “3 Mega Projects” report (대한민국 대도약 3대 메가프로젝트): ≈₩800 trillion and four memory fabs in the southwest; Chungcheong (충청) packaging hub, ₩81 trillion. [S1, S2]
  7. Gwangju briefing: Amkor Technology Korea announces ≥₩1 trillion for advanced packaging. [S28]
  8. Jeonnam–Gwangju Integrated Special City (전남광주통합특별시) launches. [S31, S7]
  9. Gwangju military airport chosen as the cluster site. [S3]
  10. Two-year land-transaction permit zone takes effect around the site. [S22]
  11. MOLIT designates ≈2.5 M pyeong as a candidate national industrial complex. [S5]
  12. Special Act enforcement decree in force. [S30]
  13. Defense ministry details temporary dispersal to Yecheon, Jungwon and Seosan. [S17]
  14. Water plan revised to use reclaimed wastewater instead of two dams. [S8]
  15. Muan national industrial complex candidate (3.47 km²) designated. [S38]
  16. Mangun-myeon selected as relocation candidate. [S18]
  17. Cabinet waives the preliminary feasibility study for the power-supply facilities. [S12]
  18. Muan International Airport runway defects found; repairs to run to H2 2027. [S25]
  19. National Assembly audit: power and water disputes; stage-1 line target moved to 2028; KEPCO puts stage-1 cost at ₩1.4 trillion. [S11, S12]
  20. Muan resident referendum on hosting the airbase (result not reported as of 13 Oct). [S20]
  21. Transmission-line groundbreaking. [S7]
  22. Sin-Jangseong (신장성) 345 kV substation completion. [S13]
  23. Gwangju domestic flights move to Muan; Honam KTX phase 2 via Muan Airport. [S25, S4]
  24. Construction of the first two fabs begins. [S7]
  25. Airbase functions temporarily dispersed to Yecheon, Jungwon and Seosan. [S17]
  26. Stage-1 supply: 3.1 GW of power and 150 000 t/d of water. [S7]
  27. Water supply capacity of 650 000 t/d. [S8]
  28. First mass production. [S7]
  29. New military base at Muan completed. [S18]
  30. Cluster power demand reaches 6.28 GW (projection). [S13]

Evidence

Close to its inputs, far from its industry, and the numbers disagree

Water, power and rail sit within about 50 km. The capital-region supply base is over 180 km away, and official figures for the grid and water differ by source.

How far the inputs are

Straight-line distance from the site centroid, km (log scale). Dashed bars use approximate locations.

1 km3 km10 km30 km100 km300 kmSongjeong KTX station2.1NWS41Reclaimed-water plant (probable)4.5NES40GIST12.1NS41Amkor packaging plant13.2NS40Sin-Gwangju 345 kV substation15.4NES40Naju Dam reservoir20.7SS40Dongbok Dam27.6ES40Muan International Airport40.8WS41Mangun-myeon (airbase relocation)41.7WS40Juam Dam reservoir41.9ES40Hanbit nuclear plant47.4NWS14Mokpo New Port57.7SWS40Saemangeum (Jeonbuk)79.0NS41Gwangyang container terminal81.5ES40Onyang, Chungcheong packaging hub184NS40Yongin cluster231NS40Incheon International Airport262NS41
FIG. 3 Distances computed from mapped coordinates (OSM, Wikipedia); not route lengths. Colours follow the factor key.

Contested figures, shown side by side

Sources give different values, and some measure different scopes. None has been reconciled here.

New 345 kV line lengthkm01020304050KEPCO: stage-1 line20–25S12Minister: new branch≈32S11July plan: total, staged≈43S13Stage-1 power supplyGW012345Gwangju city · end-20283.1S7Ministry/KEPCO plan · Jul 2026≈4S13Long-run industrial waterthousand t/d02404807209601200National plan · by 2030650 000S11Gwangju city · long-run1 060 000S7
FIG. 4 KEPCO's 20–25 km is the stage-1 line; the minister's ≈32 km is the new branch; ≈43 km is the July plan's staged total.

Drought signals in the supply basins

Indicators cited by the National Assembly Research Service fact-check.

Juam Dam storage · 2022 drought low26.2 %S9Seomjingang Dam storage · 28 Aug 202613.6 %S9Jangheung Dam inflow · 2022 vs 5-yr mean−72.2 %S90100 % (storage) · −100 % (inflow)
FIG. 5 Storage ratios and inflow change are different measures; dates differ by row.

Nine factors

Factor by factor

Choose a factor for its summary, key figures, distances from the site, assessment and open disputes. “Show on map” focuses Fig. 1.

F1 · Water supply

Mixed

Three dams plus treated wastewater are to supply 650 000 t/d by 2030; most of the originally planned dam water comes from the drought-exposed Seomjin basin[S8, S9].

Summary

The government states the four fabs need 650 000 t of industrial water per day at full build-out, and the climate-energy-environment minister told the October 2026 National Assembly audit this is deliverable[S11]. The August 2026 revision of the supply plan uses three dams and treated wastewater: stage 1 (Dongbok Dam (동복댐) and Juam Dam (주암댐), 350 000 t/d) and stage 2 (Naju Dam (나주댐) plus 200 000 t/d of reclaimed water from the Gwangju No. 1 sewage treatment plant, about 3 km from the site), to be completed by 2030[S8]. Reclaimed water is earmarked for cooling; ultrapure water (UPW) for wafer cleaning is to come from dam and river water, because sewage-derived feed is hard to bring to the ≤1 ppb total-organic-carbon level UPW requires[S8]. Contrary to the starting lead that water would come from the Yeongsan River (영산강) system, a National Assembly Research Service (NARS) review found that 84.6 % of the originally planned dam water (550 000 t/d) would come from the Seomjin River (섬진강) basin, which recorded severe drought storage levels in 2022 and 2026[S9]. The city of Gwangju separately cites an interim 150 000 t/d by end-2028 and a long-run 1.06 Mt/d, which differs from the national figure[S7].

Assessment

▲ Advantage
Three existing dams plus reclaimed water close to the site; preliminary feasibility study waived[S7, S8].
▼ Constraint
No dedicated industrial-water line to Gwangju today; pipelines and Dongbok raising still to be built[S10, S7].
? Uncertainty
Drought yield of Seomjin-basin dams; UPW feedstock quality[S9, S8].

Disputes and open questions

  • Drought resilience: a NARS fact-check cited by Rep. Koo Ja-keun (People Power Party, PPP) says the volumes' calculation basis was not disclosed and that dependence on one basin is a drought risk[S9].
  • Minister Kim Sung-hwan and Rep. Shin Jeong-hoon (Democratic Party, DP) argue Yeongsan and Seomjin water has mostly gone to agriculture and that supply is adequate[S11].
  • Whether reclaimed wastewater can feed UPW production at scale is unresolved; the ministry currently limits it to cooling[S8].
  • National (650 000 t/d by 2030) and city (1.06 Mt/d long-run) targets differ; the relationship between them is not explained in the sources[S7, S8].

Key figures

Table 1. Key figures, F1 water supply.
IndicatorValueUnitSource
Industrial water required at full build-out (government)650 000t/d[S11]
Stage 1 supply: Dongbok Dam 300 000 + Juam Dam 50 000350 000t/d[S8]
Stage 2 supply: Naju Dam 100 000 + reclaimed wastewater 200 000300 000t/d[S8]
Reclaimed-water allocation (cooling use; Gwangju No. 1 sewage plant)200 000t/d[S8]
Planned industrial-water production capacity at No. 1 sewage plant≈300 000t/d[S8]
Distance, No. 1 sewage plant to site≈3km[S8]
Dams dropped from the June plan (Jangheung, Boseonggang), 100 000 t/d each200 000t/d[S8]
Target year for 650 000 t/d capacity2030year[S8]
Interim supply target, end-2028 (Gwangju city)150 000t/d[S7]
Long-run supply target (Gwangju city)1 060 000t/d[S7]
Share of original dam allocation from the Seomjin basin (550 000 t/d)84.6%[S9]
Juam Dam storage ratio, 2022 drought low26.2%[S9]
Jangheung Dam 2022 inflow vs. 5-year mean−72.2%[S9]
Seomjingang Dam storage ratio, 28 Aug 202613.6%[S9]
Additional yield sought by raising Dongbok Dam250 000t/d[S9]
UPW total organic carbon requirement≤1ppb[S8]
UPW consumed per wafer (approx.)≈7t[S10]
Indicative water need per fab (Jeonnam vice-governor)≈200 000t/d[S16]

Spatial relationship to the site

Table 1b. Mapped F1 features: straight-line distance and bearing from the site centroid (lines and polygons to nearest vertex).
FeaturekmBearingPrecisionSource
Dongbok Dam (동복댐)27.6Eexact[S40]
Juam Lake (주암호), Juam Dam reservoir41.9Eexact[S40]
Naju Lake (나주호), Naju Dam reservoir20.7Sexact[S40]
Gwangju Environment Corp. wastewater plant (probable No. 1 sewage plant)4.5NEapproximate[S40]
Boseonggang Dam (보성강댐) — dropped Aug 202647.0SEexact[S40]
Jangheung Dam (장흥댐) — dropped Aug 202641.6Sapproximate[S40]
Yongyeon water treatment plant (용연정수장)14.6Eapproximate[S40]

Synthesis

Advantage, constraint and uncertainty, factor by factor

Table 10. Synthesis matrix. Row colours match the map layers; select a factor name to show it on the map.
Factor▲ Advantage▼ Constraint? Uncertainty
F1
Mixed
Three existing dams plus reclaimed water close to the site; preliminary feasibility study waived[S7, S8].No dedicated industrial-water line to Gwangju today; pipelines and Dongbok raising still to be built[S10, S7].Drought yield of Seomjin-basin dams; UPW feedstock quality[S9, S8].
F2
Mixed
Large nuclear and renewable output near the site, now partly exported or curtailed[S11, S14].New 345 kV line and substation needed; 2028 target is tight against historical build times[S11, S12].Peak-hour firm capacity; Hanbit unit retirements; final route and length[S10, S11].
F3
Advantage
Large, flat, state-owned site with no private compensation, next to KTX[S3, S4].Military and civil aviation must leave first; zoning restrictions[S4, S10].Expansion boundary; land-value basis for relocation funding[S5, S21].
F4
Constraint
Relocation process already at candidate stage, with temporary dispersal as a bridge[S17, S18].Fab construction depends on vacating an active airbase; law change pending[S4, S21].Muan referendum outcome and timing; pilot-training disruption[S17, S20].
F5
Mixed
Low recorded seismicity; no known active faults; flat, already-graded land[S22, S3].Adjacent river-flood risk zones; airbase vibration until vacated[S23, S10].No site-specific geotechnical, groundwater or micro-vibration data published[S22].
F6
Mixed
KTX station ≈2 km away; expressway access; two regional ports within ≈80 km[S24, S40].Regional international airport closed; ≈230 km from Yongin and ≈260 km from Incheon[S25, S40].Freight routing for wafers, chemicals and tools not published.
F7
Mixed
Research universities near the site (GIST 12 km); new contract programmes[S26].Young-adult net out-migration from Gwangju and Jeonnam[S27].Whether new programmes scale in time for 2030 production[S26, S7].
F8
Mixed
Existing OSAT anchor (Amkor) and national AI data center near the site[S28, S29].No front-end supplier base in Honam today; anchors ≈200 km from Yongin/Chungcheong ecosystems[S1, S40].Pace of supplier relocation; fab count beyond four[S1, S5].
F9
Mixed
Special Act funding rules favour non-capital regions; integrated city aligns local government[S30, S31].Fast-tracked procedures (waivers, compressed environmental review) invite legal and political challenge[S3, S33].Durability across future administrations; claims for distributed follow-on fabs[S34, S6].

Documentation

Methods, limitations and sources

Methodology and data sources

Research. The starting leads were treated as unverified. Each was checked against Korean- and English-language reporting retrieved on 13 October 2026, and every quantity was read in the article text rather than taken from search snippets. Government releases (Korea.kr) were used where located. Otherwise the report relies on national dailies, wire services (Yonhap, News1, Newsis) and regional outlets. Each factor draws on at least two independent outlets (see research/sources.md).

Attribution. Official decisions (designations, cabinet actions, enacted law) are distinguished from announced corporate plans and from targets. Contested claims are attributed to the person and party that made them. Quotations are avoided; Korean text is paraphrased.

Spatial data. Administrative boundaries are KOSTAT SGIS si-gun-gu polygons (2018 vintage) from the southkorea-maps repository, simplified with mapshaper[S39]. Feature coordinates come from OpenStreetMap elements[S40] or Wikipedia article coordinates[S41, S14]. Where a facility's exact location is unpublished, the marker uses the named administrative area's centroid or a schematic line and is flagged approximate (dashed). The airbase outline (OSM way 444717696) measures 6.01 km², which matches the 1.85 M pyeong airfield component reported in S4.

Derived values. Distances are great-circle (haversine, R = 6371.0088 km) from the vertex mean of the site outline (126.8024° E, 35.1217° N). Lines and polygons are measured to their nearest vertex. Area conversions use 1 pyeong = 400/121 m².

Charts. Every chart value is read at build time from data/factors.json, the same file that drives the tables and map, so each number has one source. Charts never combine values from different years into one bar. Targets are drawn hatched or dashed, projections in a light fill, and existing capacity solid.

Encoding. Each factor has one colour, used on the map, the factor grid, the timeline lanes and the synthesis matrix. Water is always ocean blue and power always electric blue; coral and amber mark dependencies and hazards. Assessments use shape as well as colour (▲ advantage, ▼ constraint, ◆ mixed).

Limitations and unverified items
  • Not publicly reported in any source reviewed: the land price or appraisal of the site; site groundwater conditions; site-specific typhoon exposure; freight routing for semiconductor inputs and outputs; a semiconductor-specific workforce requirement for the four fabs; the routes of the proposed 345 kV branch and of the water pipelines; the boundary of the 8.26 km² candidate complex; and the exact location of the Sin-Jangseong substation.
  • Not verified: no single official list naming all seven candidate sites was found. Five appear in press comparisons, and Naju Energy and Muan are separate national-complex projects[S10, S15, S36, S38]. The Muan referendum date and result were not reported as of 13 October 2026[S20]. Reports that the cluster could reach nine fabs, and totals of ₩896 trillion that include other investors, appeared in search results but were not confirmed in article text, so they are excluded.
  • Conflicting figures are shown side by side rather than reconciled: stage-1 line length (20–25 km, ≈32 km, ≈43 km in total) and capacity (3.1 GW vs ≈4 GW)[S7, S11, S12, S13]; the long-run water target (650 000 vs 1.06 M t/d)[S7, S8]; Solaseado's area (3.96 km² parcel vs 20.9 km² enterprise city)[S10, S15]; the Naju Energy complex budget (₩263.3 bn per MOLIT vs ₩368.5 bn per KBC)[S36, S37]; and the MOLIT designation date (29 vs 30 July)[S5, S6].
  • Source base. Most evidence is press reporting of official statements and parliamentary exchanges. Underlying documents (the NARS fact-check, KEPCO grid studies, MOLIT designation notice) were not obtained directly.
  • Geometry. The 2018 boundaries predate the 2026 merger and the reclaimed Saemangeum land. Islands under 0.5 km² were removed and lines simplified for display. Approximate markers show administrative areas, not facilities. Straight-line distances understate travel distances.
  • Basemap. CARTO tiles were planned, but on 13 October 2026 CARTO's keyless endpoint returned watermarked “API key required” tiles. The map uses the keyless Esri World Ocean Base instead (native detail to zoom 10, upscaled beyond). If the tiles fail, an embedded Korea land outline and all analytical layers still render.

References

  1. S1삼성·SK 800조 투자, 호남 반도체 허브의 꿈 '현실로'. Newsis (뉴시스), 2026-06-29. https://www.newsis.com/view/NISX20260629_0003687807
  2. S2'메가투자' 삼성·SK, AI테이터센터에 피지컬AI 까지 대규모 투자 단행. Metro Seoul (메트로신문), 2026-06-29. https://www.metroseoul.co.kr/article/20260629500465
  3. S3호남 반도체 클러스터, 광주 군 공항 부지에 짓는다···"250만평 부지, 도심·KTX역 인접". Kyunghyang Shinmun (경향신문), 2026-07-06. https://www.khan.co.kr/article/202607061655001
  4. S4248만평 넓은 부지·용수 등 강점···군 공항 기능이전 해결돼야. Kyunghyang Shinmun (경향신문), 2026-07-06. https://www.khan.co.kr/article/202607061727001
  5. S5'호남 반도체 클러스터' 첫발...광주군공항 부지 250만 평 국가산단 후보지 지정. KBC Kwangju Broadcasting, 2026-07-29. https://news.ikbc.co.kr/article/view/kbc202607290060
  6. S6광주 반도체 전력망도 2029년인데…새만금 분산 배치 '인프라 부족론' 따져보니. Jeonbuk Ilbo (전북일보), 2026-08-03. https://www.jjan.kr/article/20260803500462
  7. S7800 Trillion Won Honam Semiconductor Cluster Accelerates: Construction of Two Fabs to Begin in 2028. The Asia Business Daily (아시아경제, English edition), 2026-09-22. https://view.asiae.co.kr/en/article/2026092216323881806
  8. S8[단독]호남 반도체 용수, 장흥·보성강댐 빼고 '하수재이용수' 20만톤 쓴다. News1 (뉴스1), via Daum, 2026-08-14. https://v.daum.net/v/20260814060151080
  9. S9호남 반도체 하루 65만t 물 필요한데…가뭄 오면 어쩌나 (reporting the National Assembly Research Service fact-check). Namdo Ilbo (남도일보), 2026-09-18. https://www.namdonews.com/news/articleView.html?idxno=923843
  10. S10반도체 클러스터 유력 부지 어디... 전력망 가까운 광주? 물 풍부한 해남?. Hankook Ilbo (한국일보), 2026-06-25. https://www.hankookilbo.com/news/article/A2026062413350000239
  11. S11野 "호남 전력·물 턱없이 부족" 與 "남아돌아 수도권 송전" [李정부 2년차 국감]. Financial News (파이낸셜뉴스), 2026-10-06. https://www.fnnews.com/news/202610061816067197
  12. S12[2026 국감] 호남반도체 전력망 비용 '송곳 질의'…삼전닉스 80% 부담 (종합). Newspim (뉴스핌), 2026-10-12. https://www.newspim.com/news/view/20261012001469
  13. S13"발전소보다 변전소"…광주 반도체 산단, 전력망 삼중화에 달렸다. Korea Economic Daily (한국경제), 2026-07-10. https://www.hankyung.com/article/202607096356i
  14. S14Hanbit Nuclear Power Plant (article; installed capacity and coordinates). Wikipedia (English), accessed 2026-10-13. https://en.wikipedia.org/wiki/Hanbit_Nuclear_Power_Plant
  15. S15삼성 호남 팹 후보지 따져보니…'광주'는 인프라, '해남'은 부지 강점[3대 메가프로젝트③]. Newsis, via Financial News, 2026-06-27. https://www.fnnews.com/news/202606271000329426
  16. S16호남 반도체 투자계획 유력 후보지 3곳은…첨단3지구 주목. News1, via Financial News, 2026-06-29. https://www.fnnews.com/news/202606291027324985
  17. S17광주 군공항 2028년 이전…예천·서산·충주 분산 재배치. Seoul Shinmun (서울신문), 2026-08-14. https://www.seoul.co.kr/news/politics/2026/08/14/20260814500242
  18. S18광주 군공항 이전 후보지, 무안군 망운면 일대 선정. Seoul Shinmun (서울신문), 2026-08-28. https://www.seoul.co.kr/news/politics/2026/08/28/20260828500273
  19. S19국방부, 광주 군공항 예비 이전후보지로 전남 무안군 망운면 선정. Ministry of National Defense, via Korea.kr policy briefing (대한민국 정책브리핑), 2026-04-02. https://www.korea.kr/news/policyNewsView.do?newsId=148961950
  20. S20후보지 선정된 '광주 군공항 이전' 사업…'주민투표'만 남았다. Seoul Shinmun (서울신문), 2026-08-30. https://www.seoul.co.kr/news/society/2026/08/30/20260830500027
  21. S21광주 군공항 이전 '선 양여·국비 지원' 법 개정 주목. MTN (머니투데이방송), 2026-09-08. https://news.mtn.co.kr/news-detail/2026090810160224565
  22. S22日 구마모토 지진에 광주 반도체 입지 안전성 관심. Yonhap News (연합뉴스), via Daum, 2026-07-29. https://v.daum.net/v/UgFMJrDgGK
  23. S23'빗물 빠지지 않는 광주' 불투수 면적 25%…구도심 집중 (reporting Gwangju Research Institute policy brief). Newsis (뉴시스), 2024-07-24. https://mobile.newsis.com/view/NISX20240724_0002824253
  24. S24호남 반도체 입지 KTX용산~광주송정역 1시간30분대. Herald Economy (헤럴드경제), 2026-07-06. https://biz.heraldcorp.com/article/10799943
  25. S25무안공항 활주로 내구성 저하 확인…내년 하반기까지 전면 보강. Newspim (뉴스핌), 2026-09-22. https://www.newspim.com/news/view/20260922001071
  26. S26'인력 남방 한계선?' 호남에 반도체 인재 10만명 양성한다. Newsis (뉴시스), 2026-06-29. https://www.newsis.com/view/NISX20260629_0003687988
  27. S27청년들 떠나는 광주, 작년 인구 1만3000명 감소 (reporting Honam Regional Data Office / KOSTAT, "2025 Honam–Jeju internal migration"). Sidae (동행미디어 시대), 2026-05-27. https://www.sidae.com/article/2026052710380928963
  28. S28앰코코리아, 광주 첨단 패키징 1조 투자 약속…1000명 일자리 기대감. Jeonnam Ilbo (전남일보), 2026-06-30. https://www.jnilbo.com/news/articleView.html?idxno=90000046697
  29. S29NHN클라우드, 광주서 '국가 AI 데이터센터' 정식 개소. Byline Network (바이라인네트워크), 2023-11-03. https://byline.network/2023/11/1103_001
  30. S30정부, 반도체산단 기반시설 50~100% 지원…반도체특별법 11일 시행. Newspim (뉴스핌), 2026-08-04. https://www.newspim.com/news/view/20260804000342
  31. S3140년 만의 재결합…'전남광주통합특별시' 법안 국회 본회의 통과. Herald Economy (US edition), 2026-03-01. https://www.heraldk.com/article/2026030104255726490
  32. S32"서명 한 달 만에 4만명 돌파"…전북, 반도체 분산 배치 요구 수면 위로. Pressian (프레시안), 2026-01-28. https://www.pressian.com/pages/articles/2026012812460940768
  33. S33'호남 반도체' 진실공방..."기업 팔 비틀기" VS "선택의 문제 아냐". Money Today (머니투데이), 2026-10-06. https://www.mt.co.kr/amp/politics/2026/10/06/2026100616202138462
  34. S34"李대통령이 되레 지역 갈등 부추겨"…국민의힘, '호남 반도체' 현실성 공세. Dailian (데일리안), 2026-06-30. https://www.dailian.co.kr/news/view/1661785
  35. S35'호남 반도체' 논란에 뭉친 유의동·이준석…"용인 투자 계획, 호남으로 대체 안 돼". Dailian (데일리안), 2026-06-29. https://www.dailian.co.kr/news/view/1661077
  36. S36나주 에너지 국가산단 조성 국토부 승인 고시..개발 착수. KBC Kwangju Broadcasting, 2025-07-02. https://news.ikbc.co.kr/article/view/kbc202507020061
  37. S37나주 '에너지' 국가산단 최종 승인…"국가 전략적 거점 마련". Ministry of Land, Infrastructure and Transport, via Korea.kr, 2025-07-02. https://www.korea.kr/news/policyNewsView.do?newsId=148945348
  38. S38무안에 105만평 국가산단 들어선다...반도체·에너지 산업 거점 육성. PPSS (ㅍㅍㅅㅅ), 2026-08-25. https://www.ppss.kr/news/articleView.html?idxno=307243
  39. S39South Korea municipal boundaries, 2018 (`kostat/2018/json/skorea-municipalities-2018-geo.json`), from KOSTAT SGIS, KOGL Type 1 licence; collected 2018-12-24. southkorea/southkorea-maps (GitHub), data from Statistics Korea (통계청) SGIS, vintage 2018. https://github.com/southkorea/southkorea-maps/tree/master/kostat/2018/json
  40. S40OpenStreetMap features (Overpass API and Nominatim queries; OSM IDs given per feature in `factors.json`). OpenStreetMap contributors (ODbL 1.0), data as of 2026-05-31 (kumi mirror) and 2026-10-13 (overpass-api.de). https://www.openstreetmap.org/
  41. S41Article coordinates for: Gwangju Airport; GwangjuSongjeong station; Muan International Airport; Incheon International Airport; Yecheon Air Base; Saemangeum; Gwangju Institute of Science and Technology; Chonnam National University; Chosun University; Korea Institute of Energy Technology; Honam University; Dongshin University; Jangseong County; Mokpo; Cheongju. Wikipedia (English), MediaWiki API `prop=coordinates`, accessed 2026-10-13. https://en.wikipedia.org/